Dam in Danghara District, Khatlon Province
37°58′15″N 69°1′37″E / 37.97083°N 69.02694°E / 37.97083; 69.02694StatusOperationalConstruction began20 December 2006Opening date6 September 2011Owner(s)SangobDam and spillwaysType of damEarth fill dam with clay coreImpoundsVakhsh RiverHeight (thalweg)31.5 m (103 ft)Length385 m (1,263 ft)Spillway typeGatedPower StationTypeRun-of-riverTurbines2 X 110 MWInstalled capacity220 MW (max. planned)

Sangtuda 2 Hydroelectric Power Plant (Russian: Сангтудинская ГЭС-2; Tajik: Нерӯгоҳи барқи обии Сангтӯда-2) is a Tajik hydroelectric power plant on the Vakhsh River.

History

Construction commenced during the Soviet period in the 1980s, but halted in the beginning of the 1990s due to lack of financing. In 1995, Iran expressed interest in helping to finish the project, but an agreement was not signed until 2005. Building work restarted on 20 December 2006.[1][2]

The first unit was inaugurated on 6 September 2011 by presidents Emomalii Rahmon and Mahmoud Ahmadinejad.[citation needed]

Description

The power plant is built and operated Iranian company Sangob.[3] The turnkey contractor was Farab International Co. The project was consulted by Mahab Ghods Engineering Company and the subcontractor was Omran Maroon Engineers Company.[4] It operates simultaneously with Sangtuda 1 Hydroelectric Power Plant. It uses gates of Nurek reservoir.[3]

The dam is an earth fill dam with clay core. Its height from the river bed is 31.5 metres (103 ft) and crest length is 3,185 metres (10,449 ft).[4]

The run-of-river type power plant consist of two units able to produce 1 TWh of electricity a year. The generating equipment is manufactured in China.[5][6]

Revenues during first 12 years would be paid to Iran – and after that, ownership would be transferred to Tajikistan.[2]

References

  1. ^ "Tajikistan, Iran, Afghanistan Sign Deal On Electric Power Line". Radio Free Europe/Radio Liberty. 2006-02-21. Retrieved 2009-08-09.
  2. ^ a b "Iran starts building 180 mln usd Tajik hydroelectric power plant". Forbes. 2006-02-20. Retrieved 2009-08-09.[dead link]
  3. ^ a b "Emomali Rahmon gives start to construction of Sangtuda-2 dam". Tajik Water. 2010-11-29. Retrieved 2011-12-26.
  4. ^ a b "Omran Maroon Engineers Company Projects". Omran Maroon. Retrieved 2011-12-26.
  5. ^ "Sangtuda-2 units to be delivered by year-end". New Europe. 2009-09-19. Retrieved 2010-01-17.
  6. ^ "Iran sends equipment by air to complete Sangtuda-2 dam". AsiaNews. 2011-08-01. Retrieved 2010-01-17.
  • flagTajikistan portal
  • iconWater portal
  • iconRenewable energy portal
  • v
  • t
  • e